• Start Date: December 17, 2020
• Contract Meters: 2000m3
• General Contractor - Penn-Co Construction
Challenges: The project was scheduled to begin in May of 2020. Due to the Covid-19 pandemic the schedule was delayed by 4 months. This pushed the bulk of the concrete production into the harsh Manitoba northern winters. The main floor slab pours began on Dec 17 2020 with ambient temperature of -38 windchill of -48. The main floor slab of 1500m3 was split into 6 pours and and was completed by March of 2021.