• Start Date: September 2019
• General Contractors - Minty’s Moving and Moncrief Construction
• North 2 Rivers Bridge Replacement 6 highway 70km south of Grand Rapids.
• North Morrison creek box culvert number 6 highway 11 km south of Grand Rapids
Challenges: The project took place during the harsh Manitoba winter. Construction on the project started in September of 2019 and was completed in March of 2020. Aggregates had to be trucked to the site from Winnipeg which is a 6 hours drive. Tria products delivered on schedule.