• Start Date: February 2020
• General Contractor - Razar Contracting
Challenges: The project required all concrete materials to be bagged and shipped to the site on a winter road. Due to the Covid-19 pandemic the project freight was not able to be completed until after august 2020. The remaining freight had to be barged to site. Tria was faced with the challenge of harsh northern Ontario winters of -30 to compete the concrete. The top slab was poured January 10. 120m3 with a windchill of minus -40.